Westport in Brief!

EverythingWestport.com

Saturday, July 23, 2016

photos/EverythingWestport.com except as noted

 

And then there were four.

 

Westport Cultural Council will host its 5th annual 2016 Film Series at the Shattuck.

 

 

And then there were four.

23 proposed options for a Junior/Senior High School gleaned down to four that will be submitted to Massachusetts School Building Authority.

EverythingWestport.com

Thursday, June 23, 2016

 

By Robert Barboza 

Special Correspondent to EverythingWestport.com

 

WESTPORT – Two town boards voted unanimously on Wednesday, July 20th to send four feasibility studies for a new school building to the Massachusetts School Building Authority (MSBA) for review and consideration of financial aid for an approved construction plan. The studies will be further developed over the next few weeks in preparation for filing with the MSBA by the end of September. 

 

Selectmen and the Westport School Committee met with the town’s School Building Committee in joint session at Westport High School to review what the building committee determined to be the best options out of 23 concept plans considered over the last few weeks.

 

The School Building Committee had previously voted to recommend the four options; they were not represented by a quorum at the Wednesday meeting. 

 

Two of the endorsed concept plans going to the state authority call for new construction at the site of the closed middle school, and the other two propose renovations and additions to Westport High School, or the construction of a new facility behind the current building. 

 

Preliminary cost projections indicated that the construction of a new 91,405 square foot building at the middle school site to house grades five through eight as the cheapest option for the town to consider. The tentative price tag is $52 million, including $8.5 to demolish the existing vacant building and dispose of the hazardous materials known to be there. 

 

It was estimated that the MSBA might reimburse the town for $23 million of the $52 million projected cost, with bonding of the remaining $29 million to go before voters for consideration. 

 

The middle school was permanently closed at the start of the 2015-2016 school year, with the district shifting some students to three other school buildings, and adding modular classrooms to the Macomber School campus. For more than four years, the school district had been pursuing mandated remediation measures after the discovery of polychlorinated biphenyls (PCBs) in different parts of the building.  

 

During the last round of testing at the closed school, all rooms and areas tested were well below the Environmental Protection Agency contaminant limits for children ages 6 through 12, but the school board still decided to abandon the building and turn it back to the town. At the same time, consideration of constructing a new school building began in earnest. 

 

The second option for the former middle school site is an $87 million project that would build a 173,720 square foot combined junior and senior high school for grades five to 12. That estimate also includes the $8.5 million in demolition and disposal costs for the abandoned building. 

 

That option would likely get about $38 million in MSBA aid, with the $49 million balance to be funded entirely by the town. 

 

Both of the first two options don’t “solve the problem of correcting the deficiencies of the current high school,” noted consulting architect Jonathan Levi. Built in 1949, the high school has “reached the end of its useful life” and a replacement structure or major renovations should be considered within the next decade, he suggested. 

 

A combined renovation and expansion effort at the high school, creating 188,800 square feet of space that could accommodate grades five through 12 came with a price tag of $84 million. That plan would probably generate about $37.5 million in MSBA reimbursements, with $46.5 million left to be funded by the town. 

 

That option includes retaining both the existing WHS auditorium and gymnasium, to be connected to a new U-shaped academic wing built directly behind the existing structure, which would be demolished after the new construction is completed. It would be too difficult and too expensive to renovate the old classrooms and labs to meet current standards, Levi suggested. 

 

The fourth option on the table for MSBA consideration is the construction of a completely new combined junior and senior high school building behind the existing structure, with a projected cost of $78 million for the 173,270 square foot building. That option is likely to net about $35.5 million in state aid, leaving $42.5 million for taxpayers to approve borrowing for. 

 

Both of the plans involving new construction on the high school campus site would still leave the town with the problem of financing the $8.5 million in demolition and disposal costs for removing the old middle school so that the space could be used for other municipal purposes. 

 

Several of the other options for a new school considered the use of the nearby town-owned Santos Farm, being developed for recreational use by town youth athletic organizations. Wetlands issues and the topography of the farm site led the building committee to eliminate the property from further consideration, Levi indicated. 

 

Gutting the middle school and completely renovating the facility for re-use was also dropped from consideration, based on a $52 million estimate to completely remediate the hazardous materials in the building and on the grounds, the architect said.  

 

Each of the four preferred options for a new building will be further developed with traffic issues, water and septic needs, and other site considerations added to the feasibility plans sent to the MSBA. The building committee, project manager and architect will likely meet with selectmen and the school board again in mid-September to review those further developed “schematic reports,” said owner’s project manager Daniel Tavares. 

 

The preferred schematic plans have to be submitted to the MSBA by Sept. 29 for consideration at the authority’s November meeting, Tavares indicated. The authority’s review and feedback may result in further changes being made to one or more option plans. 

 

Building Committee co-chair Diane Baron said her committee would like to meet with the traffic consultant working on the project to discuss how traffic data and safety issues might impact the final plan that is developed.   

 

Selectmen had lots of questions for the architect and project manager, but eventually voted 5-0 to support the submission of the best option concepts to the MSBA. “This is pretty impressive,” Selectman Tony Vieira said of the feasibility study package before the vote was taken.  

 

He also cautioned officials and cable television viewers watching the meeting at home that the cost estimates were only preliminary, and were likely to change before a single best option was developed and presented to voters. 

 

Selectman Craig Dutra said the four best options chosen by the building committee “make sense” to develop further with the help of the MSBA

 

Board of Selectman Chairman R. Michael Sullivan asked Superintendent Ann-Marie Dargon why a possible regionalized school district with a neighboring town had been dropped from consideration as a solution to school space issues. 

 

“The MSBA never asked us to present this option,” Dargon explained. Dargon said that “regionalization with another district would be a long, complicated process that would take us several more years” to complete. If the four option being submitted to the MSBA encounter resistance at the state level, “we would reconsider regionalization as an alternative,” Dargon said.

 

Sending high schoolers to neighboring Dartmouth as tuition students was rejected because Dartmouth High School doesn’t have enough space to accommodate all of Westport’s senior high population, Dargon noted.  

 

 

 

Westport Cultural Council will host its 5th annual 2016 Film Series at the Shattuck.

Three documentary films will highlight the theme “Masters Of Their Craft”. 

EverythingWestport.com

Saturday, July 23, 2016

 

The Westport Cultural Council will host its fifth annual film series on three consecutive Wednesdays this summer - August 10th, 17th, and 24th at 7:00 p.m.

 

The film series is free and open to the public.  It is made possible through a grant from the Helen E. Ellis Charitable Trust and will be held at the Dedee Shattuck Gallery, 1 Partners Lane, Westport, MA.

 

This year, the Council will present three documentary films highlighting the theme “Masters Of Their Craft”.  Each film will be introduced by a guest speaker, with a question and answer period to follow.

  

Wednesday August 10, 2015.  The first film, Corita is about the life and work of Corita Kent, a former nun who became an artist, bridging the gap between religious and secular art. Creator of the "Love" stamp, she used consumer culture to create revolutionary art that spoke with the voice of a generation and became known for her pop-art serigraphs with bright splashes of colors and inspirational text. She was producing as an artist well before Warhol came onto the scene - Kent was aware of Warhol, Lichtenstein, Indiana and Ruscha to name a few and they were aware of her.  Although her work was extensively exhibited and even received broad acclaim, it did not get the degree of attention that was shown to her pop art colleagues.

Our guest speaker will be Eva Payne, a PhD Candidate in American Studies at Harvard University. She was a curatorial intern for Harvard Art Museum's exhibition on Corita Kent and the Language of Pop, and curated an exhibition of Kent's papers at the Schlesinger Library.

 

Wednesday August 17, 2015.  “First Position” is a documentary that that follows six young dancers from around the world and their arduous efforts to prepare for the Youth American Grand Prix, an annual competition for dancers ages 9-19 held in New York City judged by representatives from more than thirty major dance companies and academies. The stakes are high, with success measured in securing big career opportunities including scholarships and professional contracts. But the odds are daunting as well: only 300 out of some 5,000 hopefuls from around the globe make it to the big event.

Our Guest Speaker is Nicole Guinard, founder of En L’Air School of Dance Westport, MA. Nicole has trained since the age of seven starting with the McKeon School of Dance & Gymnastics, competing regularly and becoming back-to-back national champion at NAPS and was awarded Best Interpretation of Choreography for her lyrical solo performance. Her education continued with the Patti Eisenhauer Dance Center and Festival Ballet Providence. She regularly adjudicates dance and talent competitions and teaches Master Classes throughout New England and offers children classes in all styles of dance with an emphasis on artistry, showmanship, and strong technique.

 

Wednesday August 26, 2015"Man On Wire" has been coined by many as ‘the artistic crime of the century’, the illegal walk between New York’s twin towers was a wonder to behold.  Man On Wire recounts the fascinating story of how Philippe Petit and his friends planned and engineered the death defying act of Petit’s walk on a wire suspended between the top of the twin towers in New York on a day in August 1974 without anyone knowing it was going to happen!  What took place was the result of years of preparation by Petit with the support of his friends, each of whom offer their insights in the making of this incredible documentary that attests to the unfaltering determination of fulfilling one’s dream.

This film will be introduced by a member of the Westport Cultural Council.

 

Click here for their poster of all summer events including Masters of the Craft.

 

 

 

© 2016 Community Events of Westport.  All rights reserved.

EverythingWestport.com