Westport in Brief!

EverythingWestport.com

Sunday, April 9, 2017

photos/EverythingWestport.com except as noted

 

Additional $1.8 million sought for new police station project!

 

Local Fire Fighter and Paramedic develops CARES program to assist seniors in home safety.

 

Local architect wins majority endorsement from School Building Committee to build new Jr/Sr High School.

 

WCC awards grants for 19 projects in 2017.

 

Westport Housing Production Plan workshop scheduled for Thursday, April 27th.

 

Allens Pond Sanctuary seeks volunteers to repair damaged nest platforms, monitor breeding activity.

 

 

Additional $1.8 million sought for new police station project. 

Construction and site preparation costs soar due to tight labor market. Only two bids received for the project.

EverythingWestport.com

Thursday, April 6, 2017

Photos | EverythingWestport.com

 

By Robert Barboza 

Special Correspondent to EverythingWestport.com

 

Westport selectmen have decided to lend their support to a request for additional funding for the construction of a new police station after a meeting with the police station building committee on April 3. The building committee reported that recent construction bids for the new police station planned off Hix Bridge Road came in much higher than expected, leaving the town with the option of downsizing the building to fit the original $8.5 million budget, or seeking more money from town meeting. 

 

After reviewing a number of alternatives to the preferred building plan, selectmen voted 4-1 to put an article on the annual town meeting warrant seeking an additional $1,849,800 in town funds for the project. 

 

Town Administrator Tim King recommended that the town stick with the plans for the building as originally designed. He advised selectmen that perhaps $500,000 of the needed amount could be transferred from available town funds, with the remaining $1.3 million financed by a five-year bond. 

 

Town meeting already appropriated the $8.5 million for the project, but the building committee realized there would be a funding shortfall when the low bid for the proposed construction of a scaled-down design came in at just over $7.5 million. Based on that low bid, the estimated total project costs were pegged at $10.4 million for the preferred plans. 

 

The new station was designed to be over 16,500 square feet, but selectmen learned that a scaled back 15,729 square foot version of the facility would cost about $7.58 million to build. The building committee said that at least another $640,000 in town funds would be needed to prepare the site and equip the new station with basic furnishings. 

 

In addition to extensive site work needed for the chosen location next to the Hix Bridge Fire Station, the building committee also recommended the station be equipped with a new communications system, radio antenna, and complete furnishings that would bring total project costs to about $9.3 million. 

 

According to the police station’s architect Jeff McElravy, a Connecticut general contractor who was the low bidder on a previous police station built by McElravy’s company, Tecton Architects, PC, had declined to submit a bid even though they were pursued to do so.

 

The committee gave selectmen four other options for upgrades to the scaled-down plans, including a covered parking area, meeting and training rooms, and a rooftop cupola for the building. 

 

Restoring the classroom and meeting rooms cut from the original plans would hike total project costs to around $10.4 million, creating the $1.8 million shortfall. The most expensive option offered was a $10.9 million plan that included adding a fiber optic line network for the communications system at an extra cost of $600,000. 

 

Police Chief Keith Pelletier said he had promised voters to keep the project costs at the $8.5 million figure, and the department would be happy with a smaller footprint just to get the new station built. “Even the original $8 million is a lot of money,” he noted, saying he was uncomfortable going back to voters to ask for more money. 

 

However, building committee member Carl Tripp said most of his board was not as eager to scale back the plans to keep total project costs down. He said the committee was recommending the $10.4 million option to fund the original design for a larger building, and plans that included a new communications system and furnishings.  

 

Chairman of Selectmen R. Michael Sullivan was curious as to why the construction bids came in at 23 percent more than the original cost projections. He thought the $10.4 million in total project costs was too high, and would prefer a lower-priced option that would keep costs around $10 million. 

 

Other selectmen favored seeking the full $1.8 million needed to build the facility as planned. Pelletier said he thought an additional $1.5 million in funding was a reasonable compromise that the building committee could make work. 

 

Selectman Tony Viera favored the option requiring the $1.84 million in extra funds for a $10.4 million estimate of total project costs. He felt it would be “a mistake” to downsize the plans the committee has been working on for months. “It’s a solid plan” that the town should stick with, he suggested.  

 

King said that no matter which plan the town went with, some borrowing would be required to cover the additional costs. “The town doesn’t have the additional funds to pay for this... it would have to come from borrowing,” he noted. 

 

The town wouldn’t have to borrow the entire amount, but could reduce the debt by using some free cash or a transfer from the stabilization fund. If the town used about $500,000 in available funds, and borrowed $1.3 million for five years, the annual debt service would be about $200,000, he said. 

 

“We’re only going to do this project once, so let’s do it right,” King advised.  

 

After some discussion, Viera’s motion to put a $1.84 million request for funding before town meeting passed on a 4-1 vote. Sullivan cast the only no vote on the article, asking voters to use $500,000 from free cash or the overlay surplus, and a $1.3 million short-term bond for the remainder of the needed amount. 

 

Vieira noted that the town has about $1.2 million in the overlay surplus account, set aside for possible tax abatement requests, which could be used to help finance the project. Nearly a half million dollars of that amount has already been earmarked for capital needs in Fiscal Year 2018, he pointed out.  

 

Last year’s annual town meeting approved an $8 million debt exclusion override for a new police station, later endorsed by voters at the ballot box. Funding for a design study for the project was approved by voters at a special town meeting in December. 

 

The building committee had hoped to select a contractor by the end of March, and was planning a mid-2018 completion date, but that timetable may be pushed back by the need to secure additional funding for the project at the May annual town meeting.  

 

The current police station, built in 1975, has been under discussion for replacement for years. Pelletier has said the building is unsafe and unsuitable for a modern police department’s needs. The building has experienced flooding in the basement for some time, sustaining serious water damage and requiring the relocation of detective offices and storage areas in the basement to the Hix Bridge Road fire station. 

 

 

 

Local Fire Fighter and Paramedic develops CARES program to assist seniors in home safety.

EverythingWestport.com

Sunday, April 9, 2017

 

The Westport Cares Program is a new program created by the Fire department, the Council on Aging, and the Police Department.

 

 According to Ann Marie Peckham, Westport FF/Paramedic and Cares Program Coordinator, “The goal of the program is to provide safety items, smoke and carbon monoxide detectors among other various programs for the at-risk elderly and/or disabled residents.

 

The program is fashioned after the Somerset Fire Department’s outreach Cares program, which was a success for their residents.” 

 

After FF/Paramedic, Ann Marie Peckham moved to the Westport Fire Department, she saw the need for the program to be developed for Westport’s own residents. Working in the emergency field, she would often see patients who may be living in sub-par conditions and need additional services along with fire protection. 

 

“Their (Somerset’s) program is designed to provide outreach to these clients. With collaboration from the Westport Council on Aging, the Westport Police Department, and the American Red Cross who donate the smoke detectors, we have been able to implement a program.  Each department has its own special programs and services for our residents to assist them and keep them safe”

 

Peckham’s hope is that the Cares program continues to be a success and that “Westport residents know that we are here for them 24/7. It’s time to keep our seniors safe.”

 

Peckham’s goal is to raise awareness of the program and the many benefits it provides to Westport seniors. It’s important to give back to the community and take care of our older generation who took care of us.

 

So far, they have conducted a number of visits and have seen a respectable success. Clients were grateful for the various services and detectors installed and are now aware of the programs offered by the Council on Aging and the Police department. For the Firefighters who have participated in the program, they are making a difference and are giving back to the senior community.

 

“It is a rewarding experience when you can sit with a client in a non-emergent mode and inform them about fire and fall safety, and refer them to services they may need. Generally, we are there in emergent situations and see patients on the worst day of their lives.  It is an opportunity for residence to learn about the Fire Department, the staffing levels, the equipment we have and how we respond to emergencies.”

 

Peckham’s hope is that the Cares program continues to be a success and that our residents know that we are here for them 24/7. It’s time to keep our seniors safe.

 

For more information on our program and to schedule a safety visit, please call 508.636.1110 or email Ann Marie Peckham, FF/Paramedic and ares Program Coordinator at: ffpeckham@westport-ma.gov.

 

 

 

Local architect wins majority endorsement from School Building Committee to build new Jr/Sr High School.

But with an obvious schism between some committee members and Jonathon Levy Architects, is the still-to-be-approved project’s on-time/on-budget success moving forward in jeopardy?

EverythingWestport.com

Sunday, April 9, 2017

 

By Robert Barboza 

Special Correspondent to EverythingWestport.com

 

Nearly all of the Westport School Building Committee voted on Thursday, March 30th to stay with the custom-designed local plans for a combined middle/high school developed over the past 12 months, rather than switching to a new “model school” design that could have potentially saved the town as much as $6 million dollars in project costs.

Of the 17 building committee members present, 14 voted to stick with the locally-developed custom plans, while two others favored scrapping that “preferred option” in favor of an adapted version of the design used for the construction of Longmeadow High School in 2011. Committee Co-Chair Dianne Baron abstained from voting, indicating she still had concerns about project costs, site issues, and with continuing to work with the consulting architects developing the local plans.

 

Nearly all of the Westport School Building Committee voted on March 30 to stay with the custom-designed local plans for a combined middle/high school developed over the past 12 months, rather than switching to a new “model school” design that could have potentially saved the town as much as $6 million dollars in project costs.

 

But with an obvious schism between some committee members and Jonathon Levy Architects, is the still-to-be-approved-by-voters project’s on-time/on-budget success moving forward in jeopardy?

 

And Committee Co-Chair Diane Barron is concerned that inaccurate reporting by a local weekly newspaper over project cost-cutting could muddy the waters when seeking voter approval.

 

Of the 17 building committee members present, 14 voted to stick with the locally-developed custom plans, while two others favored scrapping that “preferred option” in favor of an adapted version of the design used for the construction of Longmeadow High School in 2011. Committee Co-Chair Dianne Baron abstained from voting, indicating she still had concerns about project costs, site issues, and with continuing to work with the consulting architects developing the local plans.

 

Superintendent of Schools Ann Dargon, Westport High Principal Cheryl Tutalo, and several other school department representatives all spoke in favor of staying with the local design; Selectmen Tony Vieira and Craig Dutra also said they preferred the custom plans despite the additional costs expected.

 

Longwood High School was built at a cost of $47.48 million six years ago, a price tag adjusted for inflation to $60 million and $65 million. Added development and site costs plus the $8.5 million estimated for the demolition of the closed middle school put total project costs at $76-$81 million.

 

At a March 22 presentation, representatives of OMR Architects, which designed the Longmeadow facility, estimated that 2018 bids for revised plans would likely come in at around $83 million, not including the non-reimbursable $2-3 million extra expense of the oversized gymnasium and walking track the building committee wants included in the plans.

 

Many members of the building committee felt that the design changes needed to adapt the model design to fit Westport’s education plans would inflate that $86 million in total project costs to nearly the same $92 million estimate for the locally-designed junior/senior high school. Although the biggest incentive to switching to the model school design was an added five percent reimbursement of eligible costs from the Mass. School Building Authority, most committee members felt the potential savings did not outweigh the disadvantages of the new plans.

 

Other potential savings would have been generated by a cap on architect’s fees that could save more than a million dollars, and a shortened design and construction time frame which could eliminate as much as $700,000 in inflationary cost increases, owner’s project manager Dan Tavares told the committee before the vote.

 

“Educationally speaking, my vote would be to support the JLA (Jonathan Levi Architects) custom-designed building,” Dargon said during a straw poll of members before the formal vote. Westport School Committee member Antonio Viveiros agreed, saying the alternative plan “was not an ideal model for Westport” for a number of reasons.

 

The alternative model school plan “would take a lot of changes to make it work” in Westport, Dutra said, with a potential for millions in added costs. “I’m not sure it’s the low-cost option,” he suggested.

 

His opinion echoed that of Vieira, who had just stated that he thought “it would be a mistake” to switch plans after a year’s work because there was some possibility of “a few million dollars” in savings.

 

Later, School Committee member Mark Carney made a similar comment, saying, “I’m not sold that it’s a $4 million difference” between the two plans. He feared greater operating and maintenance costs with the Longwood model, and extra transportation costs if athletes had to be bused back to the present high school campus because of limited playing fields in the OMR design.

 

Building committee co-chair Tracy Priestner, both an educator and a member of the Westport Finance Committee, said in the straw poll “there is a $4.2 million savings (promised)” with the model school option, “but we need to go with the best design for Westport students.” She also felt that changes to the OMR design “would cut into some of those savings” that were being projected by additional MSBA reimbursements.

 

The JLA design “suits our needs best,” she suggested, because it allows better separation of middle and high school students, a safer traffic pattern for the site, and more athletic fields. She felt the building committee could work to reduce the costs of the local design and “stay fiscally responsible” to taxpayers who must approve the project.

 

Baron, the other co-chair, said she was concerned about overall costs, noting that JLA designs are “among the most expensive per square foot” of any school construction projects. She also expressed some frustration over the sometimes difficult “working relationships” with the JLA team, and their failure to address the need to identify potential well sites for the proposed school and nearby public library and elementary school.

 

The steering committee working directly with Levi has tried some “corrective measures” to make the design team more responsive to its wishes, but those efforts have largely failed, she noted. A suggested switch to a new architect to finalize the JLA design would be too costly at this point, Baron said.

 

Town Administrator Tim King was the most vocal opponent of staying with JLA and the local design option. “I’ve been very disappointed with Jonathan Levi on this process,” he said, because his team has not always been responsive to the building committee’s orders. “I would rather take my chances” with the model school plans, he added.

 

The other vote in favor of switching to the OMR design came from educator Sue Ubiera, who said she thought the potential savings would encourage more community support for a new school. “Every penny matters,” she suggested.

 

After an hour of polling members and related discussion, Baron called for a formal vote, resulting in a 14-2 show of hands in favor of staying with the locally-designed plan. She did not choose either option before announcing, “We are staying with the custom-designed school plan.”

 

The committee recruited Town Planner James Hartnett, member David Cass, and school maintenance head Michael Duarte to reinforce the steering committee as it continues to work with Levi and his team as the group works on finishing the final schematic design to be submitted to the MSBA by May for final approval of the project by the state agency in June.

 

At the current 46.9 percent MSBA reimbursement rate, the current estimate for a $92.4 million project would net the town about $39.3 million in grant money, leaving Westport with just over $53 million to finance with voter approval.

 

 

 

WCC awards grants for 19 projects in 2017.

EveryThingWestport.com

Sunday, April  9, 2017

 

The Westport Cultural Council is pleased to announce that over $26,000 in grant funds have been awarded to nineteen community projects.

 

WCC is proud to support creative and cultural experiences in Westport for all ages.  All dollars awarded will help to bring a wide array of wonderful activities and programs throughout the year, and introduce school children to music, theater and literature.

 

Funds for these awards are from a grant from the Helen E. Ellis Trust/ Bank of America. WCC members are gratified to receive these funds in memory of a beloved artist and longtime resident of our town.

 

Each grant will give support to individuals and nonprofit organizations, teachers and students who work so hard to bring concerts, field trips, outstanding artists and exhibits that enrich and expand the life of citizens in our town.

 

Congratulations to all awardees.

 

This year’s awardees include:

 

Westport Historical Commission            A trail and symposium- Cuffee & Wainer family

Westport River Watershed Alliance         River Day

Gr. Tiverton Choir                                  Annual Concerts at St. John the Baptist Church

Westport Art Group                              Summer camp scholarships for students

Westport River Watershed Alliance         Summer science camp scholarships

Westport Historical Society                    New exhibit on Headwaters to Harbor

Westport Free Library                            Irish Magic Show for families

Westport Land Trust                              Town Concert with Cheryl Wheeler

Concerts on the Point                            Performance by classical group part of series

WCC                                                     Summer Free Film Series

Westport Elementary School                  Residency visit by authors

Westport Music Boosters                      Tickets and bus for students to NB Symphony

Westport Music Boosters                      Supports for Drama Club – costumes

Joseph Ingoldsby                                 Butterfly garden at Macomber School

The Art Drive                                         Support for marketing Open Studio

Westport Middle School                        Trip to Christmas Carol at Trinity for 7th graders

South Coast Artists                               Support for marketing 2 wkend Open Studio

Dharma Voyage                                    Master boat builder to work with students

Paskamansett Bird Club                        Support for speakers on Puffin recovery

 

Westport Cultural Council is a member of the statewide network of local cultural councils in Massachusetts and a program of the Massachusetts Cultural Council. Members of the WCC are appointed by the Selectmen and serve as volunteers to support the creative life of our town. Individuals, schools, and cultural organizations are eligible to apply for project support from their local council. Funding for cultural field trips is also available..

 

Helen E. Ellis (1889-1987) was a sculptor and Westport resident for over 50 years.  Dedicated to arts and culture, she was elected to the National Association of Women Artists and Sculptors.  During her life Ms. Ellis cultivated community-wide interests and encouraged others to develop their creative talents. The Helen E. Ellis Charitable Trust was created in her memory

 

WCC meets on the first Wednesday of each month at the Westport Town Hall Annex.  Please contact Irene Buck, Chair if you have questions.  For updates of the Westport Cultural Council, please visit www.westportculturalcouncil.org, or the Westport Cultural Council Facebook Page.

 

 

 

Westport Housing Production Plan workshop scheduled for Thursday, April 27th.

Registration is not required, but they request you pre-register for the workshop by email to WestportHousing@outlook.com.

EverythingWestport.com

Sunday, April 9, 2017

 

The Westport Affordable Housing Trust Fund has contracted with a consultant to prepare an update to the town’s Housing Production Plan, set to expire at the end of July. The town has selected the planning firm of JM Goldson community preservation + planning to prepare the plan under the oversight of the Trust.

 

Having a current Housing Production Plan is important to enable the town to reach safe harbor and have more control over potentially unfriendly Chapter 40B housing proposals. The new Housing Production Plan must be approved by both the Planning Board and Board of Selectmen before the end of June.

 

The Housing Production Plan is a state-recognized planning tool that, under certain circumstances, allows the town to influence the location, type, and pace of affordable housing development. This document establishes a strategic plan for the production of affordable housing that is based upon a comprehensive housing needs assessment, and provides a detailed analysis of development constraints due to infrastructure capacity, environmental issues, protected open space, and regulatory barriers.

 

When a Housing Production Plan is certified by the state Department of Housing and Community Development (DHCD), a local Zoning Board of Appeals’ denial of a Chapter 40B comprehensive permit for an affordable housing proposal will be upheld if the application is not consistent with the local needs outlines in such a plan. Based on 2010 census figures, the Town of Westport must produce 32 subsidized housing units for a one-year certificate of compliance with DHCD guidelines, or 64 units for a two-year certificate.

 

In order to collect meaningful public input on the new plan, the Affordable Housing Trust is encouraging participation by residents, business owners and town officials in a community workshop scheduled for 6:30 p.m. on Thursday, April 27 at the Alice Macomber Primary School, 154 Gifford Road, Westport.

 

To pre-register for the workshop, please reserve your seat by e-mail to WestportHousing@outlook.com. This is an open public meeting and registration is not required to attend, but your RSVP will help the event planners provide adequate refreshments and informational materials about housing needs in Westport.

 

For more information about the Housing Production Plan development process, contact Housing Specialist Leonardi Aray by email to Leonardi@larayarchitects.com or by calling 617.270.3912.

 

 

 

Allens Pond Sanctuary seeks volunteers to repair damaged nest platforms, monitor breeding activity.

Osprey are returning in numbers to the SouthCoast This short story was written by Gina Purtell, Sanctuary Director of Mass Audubon Allens Pond wildlife sanctuary. 

EverythngWestport.com

Sunday, April 9, 2017

 

“A new season is just getting underway, and I don’t mean spring. I mean the season of bird nesting and raising young.  So many of our avian neighbors are here for this season alone, living half or more of their life someplace further to the south. 

 

 

Among those are the osprey, our emblematic bird of Buzzards Bay and the estuaries and other wetlands that feed it.  One might think that a bird that spends our coldest months in warmer climes is ill-adapted for snow and sleet but in fact, these are fantastically hardy birds. Less concerned about their own comforts, they time their arrival at our shores to the availability of fuel to support their young: the herring. 

 

While they sample from a variety of fish, herring are their staple.  As the herring begin to return, so do the osprey.

 

The first reports of bird sightings trickled in on March 18th and 19th but it wasn’t until March 21st that we heard of an osprey standing watch upon a nest platform, presumably to await his mate.

 

They endure high winds and cold rains, even snow, in the weeks ahead with the faith that herring will nourish the egg-producing, and incubating, female. 

 

Mass Audubon’s team at Allens Pond Wildlife Sanctuary will be repairing damaged nest platforms and then monitoring the breeding activity at nearly 90 nests in the Westport River/ Allens Pond Important Bird Area. This project is funded by project sponsors and executed with tremendous volunteer help.” 

 

Those wishing to support the work in any way are invited to contact the team at allenspond@massaudubon.orgTo participate in an intensive, day-long dive into the lives of osprey, the Sanctuary is also offering an Adult Field School on Saturday, June 24th. 

 

To learn more about these programs, and to register online, go to: www.massaudubon.org/allenspond.

 

 

 

© 2017 Community Events of Westport.  All rights reserved.

EverythingWestport.com