Westport gets a new south end fire station.

EverythingWestport.com

Tuesday, August 04, 2009

 

Sunshine provides welcome relief for soggy project. - Tuesday, August 04, 2009

 

Wet conditions continue to hinder work.  – July 29, 2009

 

The walls are going up.  – June 30, 2009

 

Fire station on a firm footing!  - June 22, 2009

 

Westport’s new “firebarn” is underway!  - May 30, 2009

 

Ceremonial shovels hit the dirt as Fire Station 1 gets underway!  - May 5, 2009

 

 

It’s a go!

EverythingWestport.com

Tuesday, August 04, 2009

 

After a lengthy period of failed ballot questions and voter frustration over high costs, the new south end fire station is finally underway, full steam ahead.

 

The results-oriented site superintendent is leaving no stone unturned in getting this project done on-time and on-budget. “It’s my life’s work,” Gary Bessette said. “It’s what I do.”

 

EverythingWestport.com will follow the work from start to finish. See photos and get all the news first, here, on-line. Follow our blog weekly!

 

Click here to read article and view photos of groundbreaking ceremony.

 

Click here to view photos of site clearing.

 

Click here to view all high-resolution photos of on-going site work.

 

Click here to view high-resolution photos from Chief Legendre’s fire station informational meeting held June 4, 2008.

 

Click here to get an early history of the Westport Fire Department.

 

View the high resolution photos of on-going fire station construction   56 photos    |   Dial-up speed   |   Broadband/DSL speed   |

 

Sunshine provides welcome relief for soggy project.

EverythingWestport.com

Tuesday, August 04, 2009

 

rsz_4.jpgIt’s amazing how much progress can be made with a few days of warm sunshine. “Things are starting to clip along,” said site super Gary Bessette.

 

With the water level receding through pumping and dryer air, the damp-proofing and water-proofing of the foundations and elevator pit are almost finished (photo below, center). “The concrete had to be dry prior to damp-proofing,” Bessette said.

 

Damp- and water-proofing are not complicated processes but they have to be thorough ones. As planned, extra water-proofing was necessary. “The elevator pit had to be waterproofed, and that required a rubber gasket between the footing and foundation, and a rubber membrane wrapped around the outside foundation (photo below, right),” Peter Koczera said.

 

Left: Patrick of MRL Construction digs a pump drain-hole with a mini-backhoe while its big brother is in the background grade-leveling construction-quality fill in the ground-level apparatus bay.

 

The outside foundation walls are covered with rigid, foam insulation board to prevent the stone and gravel backfill from puncturing and scrapping the damp-proof material off of the foundation surface.

 

“The masons should start laying their 8” block on the outside west wall this week,” Bessette said. “Then residents passing by will see some real progress.”

 

The gravel and construction quality materials’ base is being spread and compacted (photo below, left) as this article is being written, and you should expect to see floors being poured in the immediate future.

 

The radio tower concrete pad has been poured.

 

 

 

t1.jpg t2.jpg t6.jpg

 

 

Wet conditions continue to hinder work at the new South End Fire Station.

EverythingWestport.com

Wednesday, July 22, 2009

 

rsz_36.jpgA slight trace of concern crossed Peter Koczera’s faced as he looked into the water-filled form that was to be a concrete base for a new radio tower. The Architectural Consulting Group representative had reason for concern. Unrelenting rains have “slowed our progress but our course is sure,” said site supervisor Gary Bessette.   

 

“These rains have created an unusually high water table,” Koczera. “We have two, 2-inch pumps going day and night. 99% of our concrete footings and foundation walls have been poured, but the new walls have to be stripped and dried out so we can damp-proof them.”

 

Koczera, Westport’s owner’s project representative, is responsible for overseeing construction of the new south end fire station, ensuring that all work, materials, and erection techniques comply with the architect’s plans. Not an easy task when you throw rain into the mix.

 

“Progress has been good,” said site supervisor Gary Bessette. “We’d like to do better. Right now we can’t do compactions because the soil is too wet. However, we do track the weather pretty closely, online, and we’re always ready to proceed when it breaks.”

 

The Barr Construction supervisor remains confident the project will be completed on time. “We’re about three weeks behind,” Bessette said, “but we’re still shooting for a July, 2010 occupancy date. We have a revised plan to make up the time.”

 

Koczera, in between giving us a tour of the site, explained that the new radio tower’s main strength is to penetrate buildings, particularly metal ones, and in doing so better communicate with the firefighters’ lapel-based radio systems. “The range is obviously important when we talk about the new 100’ tower,” Koczera said. “But communicating with firefighters while in burning buildings is vital.”

 

Out-of-sight is not necessarily out-of-mind!

Koczera made the observation that 75% of the fire station construction is really in-ground, and it’s not only the footings and foundation. “We have several large underground water systems: 33,000 gallon water storage for fire control and tanker truck use; a tight-tank, waste-water collection cistern for the apparatus bays (collects hazardous spills and cleaning fluids); service drainage system for water run-off leading to an on-site retention pond; and septic system and town well. 

 

And extra waterproofing is necessary because of the high water table. “The elevator pit has to be waterproofed, and that requires a rubber gasket between the footing and foundation, and a rubber membrane wrapped around the foundation,” Koczera said. “We also put an additive into the concrete to resist water seepage.”

 

t38.jpgt40.jpgt41.jpg

From the left: (1) Comely Jen of MRI Enterprises lends a guiding hand to a massive shovel while moving an idled soil compactor; (2) foundation forms ready to be stripped; and (3) drainage system will handle surface run-off into an on-site retention pond.

 

The damp-proofing of the concrete walls prevents long-term exterior surface damage due to water erosion. Environmental factors are a principal source of concrete deterioration. Concrete absorbs moisture readily, and this is particularly troublesome in regions of recurrent freeze-thaw cycles. Freezing water produces expansive pressure in the cement paste or in nondurable aggregates. According the old house website, “carbon dioxide, another atmospheric component, can cause concrete to deteriorate by reacting with the cement paste at the surface”.

 

“We can’t damp-proof the walls until they’re dry,” Koczera was quick to point out.

 

“Our electrical and gas systems are underground,” Koczera said, “and the water vault for the station’s fire protection system is an astounding 55’ long, 14’ wide, and 9’ deep.” 

 

The new CVS building up on Route 6 seemed to spring up overnight once started, but commercial building requirements are far different than state-funded public facilities. “Our elevator is required because we are a multi-level public building. Inspection and construction oversight is far more complex as we follow stricter architectural codes,” Koczera said.

 

Be that as it may, passing motorists seem to notice little progress. “A lot of our project is in ground,” Koczera said, “and that’s where the heavy rains have hurt us most. We have accelerated our planning, and we hope to make up the lost time. Once in-ground construction is completed, the building will go right up. Community residents will get a sense of real accomplishment.”

 

Going green.

What’s next? “The committee is already discussing green or eco-friendly elements: wind turbine, energy efficient building components (insulation, low E glass, etc.) and implementing energy codes that hopefully will produce some energy savings reimbursement from NStar. The town wants an energy-efficient building.”

 

We looked up at the 80’ trees around the building site. “It’ll have to be a high one (wind turbine,)” Koczera said.

 

 

The walls go up. Work continues.

EverythingWestport.com

Tuesday, June 30, 2009

rsz_34.jpg rsz_28.jpg

Left: a Turner Brothers' foreman attaches the electrical conduit pass-throughs in the wall’s rebar before the forms go up. Right: Workers put up form partitions previously coated with a lubricant to provide a smooth, non-stick surface for the poured concrete.

 

The rainy weather in the past week kept the job site closed down several days reports site super Gary Bessette. The sumps are keeping up with the influx of ground water, and the only real issue is not being able to pour concrete under wet conditions. Hope is high as good weather is on the way! Bob of Griffin Electric (lower right) is precutting the service conduits for installation in the walls prior to pouring.

 

t26.jpg t32.jpg t30.jpg

 

 

 

rsz_25.jpgFire station gets on a firm and even footing.

EverythingWestport.com

Monday, June 22, 2009

 

Crews work the “the stick” to pour the footings and foundations before more heavy rains sets in (picture left). However, real progress is being made despite the weather says site super Gary Bessette and Fire Chief Legendre.

 

“Despite the constant rain we’re making some headway in the footings and foundations,” says site super Gary Bessette. The fire chief agreed. “We’ve had a real wet spring. The temporary sumps are doing a good job in draining the excavation.”

 

Turner Brothers Concrete LLC had their hands full setting the footing and foundation forms, and tying the rebar in preparation for the pouring of the concrete. Over the last two weeks, the crew dodged rain drops while pouring the concrete.

 

A Turner Brothers’ employee worked the transit and kept footings on an even level as the 110’ “stick” extended out over the construction site and allowed crews to direct the pumped concrete into the forms, topping them off at the correct elevation..

 

t9.jpg t17.jpg t21.jpg

From the left: (1) Octavio and Daniel of Turner Brothers tie off the rebar; (2) Patrick directs the 110’ “stick” with a “gameboy-like” wireless remote control unit; and (3) Turner Brothers’ workers fill the forms with pumped concrete, making the job fast and easy.

 

Westport’s “new firebarn” is underway!

EverythingWestport.com

Saturday, May 30, 2009

 

 

rsz_7.jpg“We’re draining the hole,” says site super Gary Bessette. “The heavy spring rains have raised the water level and we need to dry out the excavated pit before we pour the footings and foundation.” The temporary sumps worked overtime to keep up with the high water tables

 

After a lengthy period of failed ballot questions and voter frustration over high costs, the new south end fire station is underway, full steam ahead.

 

The results-oriented site superintendent is leaving no stone unturned in getting this project done on-time and on-budget. “It’s my life’s work,” Bessette said. “It’s what I do.”

 

Telephone and electric are hooked up, land elevations are realized, and the setup and pouring of concrete will commence within a matter of days.

 

 

 

 

Click here to read article and view photos of groundbreaking ceremony.

 

Click here to view photos of site clearing.

 

Click here to view all photos of on-going site work.

 

 

t4.jpg

 

rsz_8.jpg

 

At ease, men! Heavy equipment in full field dress getting a weekend leave.

 

 

 

 

 

 

 

t23.jpgCeremonial shovels hit the dirt as Fire Station 1 gets underway!

EverythingWestport.com

Tuesday, May 5, 2009

Photos © 2008, 2009 EverythingWestport.com

 

Fire department personnel and town officials broke ground for Westport’s new south end fire station on Tuesday at 1:20 p.m. For some it was none too soon.

 

“Before the first fire house in 1928, Westporters used the bucket brigade’” Calvin “Hoppy” Hopkinson said in an interview last year. “But then a group of Westport volunteer firefighters started an association (Westport Volunteer Fire Association,

Ken Nickleson – current president) and put up a fire station in Central Village on a lot that old Charlie Wood leased to the town for as long as the land was used for fire prevention purposes,” Cal said.

 

That purpose is coming to end as the Town of Westport broke ground for a new Fire Station for a projected cost not to exceed $7 million dollars.

 

In contrast, the 1928 Central Village fire station built by volunteer firefighters, and later expanded in 1978 with the help of Diman Regional Vocational students, came from privately raised capital and donations, and at no cost to the town.

 

Above photo, from the left: former selectwoman and committee member Veronica “Ronnie” Beaulieu, committee member John “Jack” De Veuve, Fire Chief Brian Legendre, current selectmen and committee members Steve Ouellette and Paul Schmid, former selectwoman and committee chairwoman Liz Collins, Deputy Fire Chief Allen “Sam” Manley, and committee member Warren Messier.

 

t8.jpg t13.jpg t30.jpg t0.jpg

From the left: (1) Liz Collins shares a quiet laugh with Fire Chief Brian Legendre; (2)     (3) Deputy Fire Chief Allen Manley (right) shares a moment with his grandfather, Charlie Keith, who was a Westport fireman in the early 1940’s with Cukie Macomber and Calvin Hopkinson - selectman Paul Schmid looks on; and (4) an emotional Fire Chief Brian Legendre thanks the many individuals responsible for making the south end fire station a reality.

 

Click here to view more photos of the groundbreaking ceremony.

 

So you can see why the path to get here was not always easy.

 

It was a long, hard road, and the Fire Department had been turned back many times. Contentious from the start, the proposed town safety complex was viewed as too expensive and not necessary. The reality of the situation was 13.5 million dollars was a lot of money for a town of thrifty farmers used to “making do”.

 

t1.jpgThe new station is five times larger than the 1928 building that at first housed a brand-spanking new 1928 Maxim pumper (shown left). “She was a beauty,” Hoppy had said. “But boy was she expensive, almost $8000!”  In contrast, the recent ladder truck obtained by the town with assistance from Homeland Security cost about $605,000.

 

According to Chief Legendre, who is also head of the building committee, the new station house “will bring together the department’s administrative staff, the fire chief and his administrative assistant, the deputy chief and fire prevention officer.” The spacious basement will contain a training room that will double as a 24-hour emergency operations center.

 

 

 

t1.jpg  t2.jpg  t4.jpg

 

Click here to view high-definition versions of the above photos and other photos from Chief Legendre’s fire station informational meeting held June 4, 2008.

 

Click here to get an early history of the Westport Fire Department.

 

rsz_0.jpgBARR General Contactors out of Putnam, Connecticut wasted little time getting underway. A 250+ foot artesian well was in place in January, and ground clearing was finished up during the groundbreaking ceremony.

 

John Brightman (pictured left) and his crew from Brightman Lumber in Assonet schooled our community in lumber jacking as three men in three days cleared the site and trucked out the lumber without ever touching a chainsaw. Men and their logging machines.

 

Wood chips, dirt, smoke and leaves flew as Brightman’s John Deere 843J wheeled feller buncher (pictured below) applied a death grip to the trees and ripsawed through them as if they were toothpicks.

 

John’s son Eddie, better known as a woodsman competitor in New England, neatly handled the cutting, stripping and stacking chores as if he were playing “pick-up sticks.”

 

“If my father and grandfather had this equipment,” John Brightman quipped, “there wouldn’t be a tree left in New England!”

 

Click here to view more photos of the site clearing.

 

t10.jpg t16.jpg t5.jpg t6.jpg

 

The Fire Station Building Committee awarded a $4,350,750 construction contract to BARR General Contractors in April of this year. The project manager is Architectural Consulting Group of New Bedford. According to Fire Chief Legendre the town’s contract with BARR is fixed, and any sub contractor’s bid that may change will be “eaten” by BARR. “They will assume the liability,” he said. “However,” the Chief added, “I believe the project will come in under cost.”

 

rsz_6.jpg  t17.jpg

Left:  Fire Chief Brian Legendre receives the word and congratulations from Town Clerk Marlene Samson as the precinct tallies from the special ballot question conducted June 17, 2008 show that the votes cast were more than 2 to1 in favor of a new south end fire station. “I’m surprised by the margin,” Chief Legendre said. “I’m really pleased the community supported the fire department.”  Right: Chief Legendre pitches for the new fire station at one of many informational meetings held in town prior to the special ballot question.

 

 

- - - - End - - - -

 

© 2009 Community Events of Westport   All rights reserved.